The West Bend School District Update is published weekly (twice-monthly during the summer) and sent via email to all district families and staff; if you have a child enrolled in the school district and an email address on file with Skyward, you receive the newsletter. In addition, anyone else can receive the newsletter via email. If interested, please fill out this form to be placed on the distribution list.

Find district publications, press releases, media coverage, and other official communications from the West Bend School District.

Publications & Press

Learn more about WBSD’s high school configuration planning process and stay informed as new information becomes available.

High School Timeline Updates

November 10, 2026

West Bend High School Fire Recovery Update

Restoration work continues at West Bend High School, with nearly 100 crew members working on site since last Wednesday, including throughout the weekend. Teams are completing inspections, cleaning and other necessary restoration work as quickly and carefully as possible. While much of this work may not be immediately visible, it is essential to preparing the building for students and staff to return. 

Work is Underway
Second Floor

Crews have removed the majority of the ceiling tiles in the second-floor corridors, allowing them to inspect and clean areas above the ceilings. They are using HEPA vacuums to address dust and air scrubbers to provide additional air filtration. 

The Nifty and the surrounding area have been enclosed and will remain closed for inspectors, investigators, and restoration professionals. The fire was contained to the back kitchen area.

The photos show the Nifty Nibble fully enclosed, exposed ceilings, and ceiling tiles bagged for removal.

First Floor

Cleaning is underway across the first floor. Crews have established designated work areas and installed barriers at stairwells to help manage dust and keep work areas separated from surrounding spaces. The picture shows an example of how space is separated and marked. Air scrubbers are also in place throughout the first floor to support filtration during restoration activities.

Coordination and Next Steps

In addition to the work happening inside the building, the project team is working closely with the insurance adjuster, restoration professionals and district staff to review building conditions, assess completed work, and identify areas requiring additional attention.  Once this work is complete, the district will coordinate with the city to determine the requirements and next steps to restore occupancy.

Current priorities include:

  • Continuing detailed cleaning in areas throughout the first floor.
  • Continuing inspection, HEPA vacuuming, and cleaning throughout the second-floor corridors.
  • Maintaining air filtration equipment and designated work areas as restoration continues.
  • Evaluating conditions and identifying any additional work needed as the process moves forward.

We know students, staff and families are eager to return to West Bend High Schools, and we share that goal. Crews are moving as quickly as possible while completing inspections, cleaning and approvals required before the building can safely reopen.

We will continue to provide updates as the work progresses and we gain a clearer understanding of the remaining work and reopening timeline. Thank you for your continued patience.  

school hallway with cleaning supplies

Second floor hallway with the Nifty Nibble covered on the right. 

bags of garbage in the hallway

Second floor with exposed ceilings and ceiling tiles bagged for removal.

hallway of a high school

First floor with a stairwell closed.